Under Construction Projects |
||||||||||||
Sr.no. |
Name of Project |
Type of Project |
Sub Basin |
Taluka |
District |
Total I.C.A. (ha) |
Canal Left/ Right |
Total Canal Lenght (km) |
Status of Work |
Length of Canal completed (Km) |
I.C.A. of Canal created |
Remarks |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
1 |
Mukne |
Major |
Darna |
Igatpuri |
Nashik |
19912 |
-- |
-- |
85% work completed. |
-- |
-- |
Express canal from |
2 |
Bhavli |
Major |
Darna |
Igatpuri |
Nashik |
6545 |
-- |
-- |
20% work completed. |
-- |
-- |
N.M.weir to irrigate |
3 |
Waki |
Major |
Darna |
Igatpuri |
Nashik |
8607 |
-- |
-- |
15% work completed. |
-- |
-- |
42298 ha.of |
4 |
Bham |
Major |
Darna |
Igatpuri |
Nashik |
10512 |
-- |
-- |
Work not started due to forest problem. |
-- |
-- |
Aurangabad dist. |
5 |
Ozerkhed |
Major |
Kadwa |
Dindori |
Nashik |
12960 |
Left |
49 | Canal in progress | 47.00 |
10178 |
Dam completed in 1974 |
6 |
Punegaon |
Major |
Kadwa |
Dindori |
Nashik |
6984 |
Left |
63 |
Canal in progress |
12.00 |
950 |
Dam completed in 1985 |
7 |
Kadwa |
Major |
Darna |
Igatpuri |
Nashik |
10117 |
Right |
88 |
Canal in progress |
87.00 |
8811 |
Dam completed in 1982 |
8 |
Kashyapi |
Medium |
Godavari |
Nashik |
Nashik |
5817 |
-- |
-- |
85% work completed. |
-- |
-- |
Storage for Gangapur |
9 |
GautmiGodavari |
Medium |
Godavari |
Trimbak |
Nashik |
6908 |
-- |
-- |
30% work completed. |
-- |
-- |
Storage for Gangapur |
10 |
Waldevi |
Minor | Darna |
Nashik |
Nashik |
1481 |
Right |
5 |
40% work completed. |
-- |
-- |
-- |
11 |
Upperkadwa |
Minor |
Darna |
Igatpuri |
Nashik |
1495 |
Right |
16.5 |
Work order is not issued. | -- |
-- |
-- |
12 |
TalegaonTrimbak |
Minor |
Darna |
Igatpuri |
Nashik |
464 |
Left | 15 |
Canal in |
13.00 |
223 |
-- |
|
Right |
10.3 |
progress |
9.30 |
159 |
-- | ||||||
13 |
Anjneri |
Minor |
Godavari |
Trimbak |
Nashik |
274 |
Right |
9.24 |
Work in initial stage |
-- |
-- |
-- |
14 |
RaulasPimpri |
K.T. |
Kadwa |
Niphad |
Nashik |
464 |
-- | -- |
80% work completed. |
-- |
-- |
-- |
15 |
KhedleZunge |
K.T. |
Godavari |
Niphad |
Nashik |
1942 |
-- | -- |
40% work completed. |
-- |
-- |
-- |
16 |
RajangaonDesh. |
L.I. |
Godavari |
Kopergaon |
A'nagar |
507 |
-- | -- |
Civil work completed |
-- |
-- |
-- |