KARANJWAN PROJECT
I
Location
III
Yield
1
Place
Karanjwan
Catchment Area
248
Sq/K.m.
2
Taluka
Dindori
75% dependable yield
173.30
Mm3
3
District
Nashik
50% dependable yield
4
Latitude
20-18-00
IV
Submergence
5
Longitude
73-46-00
Submergence Area
1482
Ha.
6
Sub-Basin
Kadwa
Submerged villages
--
7
Year of Start of Work
1966
Affected families
8
Year of Completion
1974
Affected Persons
II
Cost of The Project
V
Dam
Origional A.A. Cost
1428.98
Lakhs
Max. height of Dam
39.31
M.
Year of A.A.
1969
Dam Length
2.09
K.m.
Revised A.A.Cost
18998.18
W.W. Length
397.50
Year of R.A.A.
1999
Total Storage
175.57
Live Storage
166.22
Dead Storage
9.35
Water for Non Irrigation
58.59
Back