( Rs. in Lacs )
1) ADMINISTRATIVE APPROVAL
Particulars |
Chief Engineer |
Supt. Engineer |
Executive Engineer |
Dy. Engineer |
| 1) Non Residential buildings. | 25 |
2.5 | 0.5 | 0 |
| 2) Residential buildings. | 25 | 2.5 | 0.5 | 0 |
| 3) Ps. & Es. for Major & Medium | 25 | 0 | 0 | 0 |
2) TECHNICAL SANCTION
Particulars |
Chief Engineer |
Supt. Engineer |
Executive Engineer |
Dy. Engineer |
| 1) Origional works under major head | Full Power | 62 | 25 | 0 |
| 2) Ordinary repairs | 0 | Full Power within budget. | Full Power within budget. | 0.50 |
| 3) Special repairs | 0 | Full Power within budget. | 5.00 | 0.50 |
| 4) Special Tools & Plans | Full Power | 12.50 | 2.50 | 0 |
3) ACCEPTANCE OF TENDERS.
Particulars |
Chief Engineer |
Supt. Engineer |
Executive Engineer |
Dy. Engineer |
| Tender Acceptance | Full Power | 125 | 25 | 1.00 |